Progress on Mothotlung water pump motor installation

MADIBENG – The process of installation of the spare motor for Mothotlung pump has commenced. The spare motor required a new electricity panel in order to function properly.

The installation process of the said panel is currently underway at the Brits Water Treatment Plant. It is envisaged that the installation processs of the panel will be completed by today (Wednesday, 27 December 2023)-subsequently the Mothotlung pump would then be switched on.

In the meantime, the water rationing process between the Mothotlung and Letlhabile reservoirs’ supply lines is continuing. The rationing process is being implemented in 24-hour intervals and affects water supply to Letlhabile, Mothotlung, Damonsville and parts of Mmakau.

The Municipality appeals to residents/consumers that are receiving water to use it sparingly. Any development regarding this matter shall be communicated accordingly.